SITUATION:

In shenzhen China, new stadiums and entertainment facilites were built in preparation for Universiade 2011. As the event date approached, the construction schedule was behind and the flooring needed to be installed in a short time frame. Once the construction site was ready, ARDEX was asked to provide a fast track solution to the corridor space of the Shen Zhen Stadium.

CHALLENGES:

  • Large size area (5000 m2 / 53,821 ft2)
  • Expedited installation time frame
  • Cold temperatures
  • Heavy and frequent foot traffic

SOLUTION:

In this situation, ARDEX recommended ARDEX K320 High Early Strength Wear-resistant Self-leveling Topping. ARDEX K320 is an extremely durable product and is appropriate for high traffic areas. ARDEX K320 is walkable in just four hours, allowing foot traffic and additional work to take place quickly after the installation.

Following correct substrate preparation protocol, ThyssenKrupp Xervon mechanically prepared the corridor area. By mechanically preparing the substrate, the installers could be sure all contaminates were removed so the ARDEX K320 would properly bond to the substrate. Once the installers created a suitable surface profile, a layer of ARDEX P 51 Primer was applied. ARDEX P 51 is a solvent-free primer used over standard absorbent concrete to seal and improve the bond of ARDEX underlayments and toppings.

Once the ARDEX P 51 was completely dried, the concrete substrate was ready to receive ARDEX K320, as the final wear surface. Once the ARDEX K320 was poured and properly protected, construction trades could continue their work while walking on the new floor. Being such a high profile project, Shen Zhen Stadium demanded high-strength and aesthetically pleasing products to complete the design.

ARDEX provided technical support and quality customer service throughout the installation. Both the owners and ThyssenKrupp Xervon were pleased with the final result.